Light-Up Kwara: Firm Releases Roll-Out Plan For Phase 2

Rubitec Power Limited, one of the two firms executing Light-Up Kwara (LUK), the solar-powered streetlight project of the Kwara State government, has released a comprehensive installation roll-out plan for the second phase of the project.

Governor Abdulfatah Ahmed of Kwara State

The roll-out plan, which was made available by the State Ministry of Energy, indicated that civil works component and the streetlight installation will be covered in three phases over a period of six months.

See also  Oba Of Lagos Bombshell

For section 1, a total of 256 poles will be deployed, covering 8.70km of roads across three routes within the Metropolis, including Kulende Estate Junction – FCMB Murtala road, Maraba – Oja-Oba and General Roundabout – Oja-Oba.

While for section 2, 392 poles will be erected across six routes, covering 9.952km. The routes to be covered are Michael Imodu – Offa Garage, Offa Garage – Unity roundabout, Unity roundabout – FCMB Murtala, Geri Alimi – CAILS and other roundabouts within the Metropolis.

See also  Nigerian Breweries Commissions Classrooms, Facilities In Imo State

The road length to be covered under the third phase is 6.36km with 196 poles installed across four routes including Emir’s road – Post Office, Balogun Fulani – Gambari, Yebmot roundabout – Adeta roundabout and Abdulkadir road, Ilorin.